Project resilience as network robustness
- URL: http://arxiv.org/abs/2604.17417v1
- Date: Sun, 19 Apr 2026 12:55:13 GMT
- Title: Project resilience as network robustness
- Abstract summary: Some project members are specialists undertaking only few tasks, whereas other are generalists and are responsible for the success of many tasks.<n>The reliance of a project on a few key people can lead to severe economic losses and delays.<n>We develop a novel method to assess project vulnerability by looking at it from the lens of network robustness.
- Score: 0.552480439325792
- License: http://creativecommons.org/licenses/by-nc-nd/4.0/
- Abstract: Engineering projects are the result of the combined effort of their members. Yet, it has been documented that labor division withing projects is unevenly distributed: some project members are specialists undertaking only few tasks, whereas other are generalists and are responsible for the success of many tasks. Moreover, the latter are often facilitators of project integration. Such a workload distribution prompts one question: how resilient is a project to key personnel loss? Far from being a theoretical problem, the reliance of a project on a few key people can lead to severe economic losses and delays. We argue that current methods to estimate such a risk are unsatisfactory: some methods offer a best-case estimate and are, therefore, too optimistic; other methods fail to capture project fragmentation leading to biased estimates and unrealistic consequences in many settings. In this paper, we develop a novel method to assess project vulnerability by looking at it from the lens of network robustness. We compare our method against existing alternatives and show that it offers better and more consistent estimates of project resilience to personnel loss.
Related papers
- Predicting Agile Success: The Critical Few Factors [0.0]
The study developed a novel model that can be used to evaluate and measure project success.<n>This research found that a few critical factors significantly contribute to Agile project success.
arXiv Detail & Related papers (2026-08-06T16:18:13Z) - Before Thinking, Learn to Decide: Proactive Routing for Efficient Visual Reasoning [87.18590662029432]
We propose PRP, a Proactive Routing Paradigm that enables early decision-making by jointly evaluating the competence of both the draft and target models.<n>Our draft Rating Learning (DRL) equips the draft model with an internal confidence estimator, while Joint Rating Learning (JRL) predicts how well the target model can handle a given query.<n>These ratings enable fine-grained, instance-level textbfProactive Routing and substantially accelerate inference without compromising overall performance.
arXiv Detail & Related papers (2026-06-29T12:30:24Z) - Lessons from a Big-Bang Integration: Challenges in Edge Computing and Machine Learning [52.86213078016168]
The project faced critical setbacks due to a big-bang integration approach.<n>The study identifies technical and organisational barriers, including poor communication.<n>It also considers psychological factors such as a bias toward fully developed components over mockups.
arXiv Detail & Related papers (2025-07-23T07:16:45Z) - A Trustworthy Multi-LLM Network: Challenges,Solutions, and A Use Case [59.58213261128626]
We propose a blockchain-enabled collaborative framework that connects multiple Large Language Models (LLMs) into a Trustworthy Multi-LLM Network (MultiLLMN)<n>This architecture enables the cooperative evaluation and selection of the most reliable and high-quality responses to complex network optimization problems.
arXiv Detail & Related papers (2025-05-06T05:32:46Z) - Towards an Interpretable Analysis for Estimating the Resolution Time of Software Issues [1.4039240369201997]
We build an issue monitoring system that extracts the actual effort required to fix issues on a per-project basis.<n>Our approach employs topic modeling to capture issue semantics and leverages metadata for interpretable resolution time analysis.
arXiv Detail & Related papers (2025-05-02T08:38:59Z) - Efficient Portfolio Selection through Preference Aggregation with Quicksort and the Bradley--Terry Model [0.0]
How to allocate limited resources to projects that will yield the greatest long-term benefits is a problem that often arises in decision-making under uncertainty.<n>We propose comparison rules based on Quicksort and the Bradley--Terry model, which connects rankings to pairwise "win" probabilities.
arXiv Detail & Related papers (2025-04-06T23:16:30Z) - Design of mechanisms for ensuring the execution of tasks in project planning [0.0]
The paper reports an analysis of aspects of the project planning stage.<n>It takes into account restrictions on financial costs and duration of project implementation.<n>Models of the task of constructing a hierarchy of tasks and other tasks that take place at the stage of project planning were constructed.
arXiv Detail & Related papers (2025-01-02T13:47:20Z) - A Survey of Confidence Estimation and Calibration in Large Language Models [86.692994151323]
Large language models (LLMs) have demonstrated remarkable capabilities across a wide range of tasks in various domains.
Despite their impressive performance, they can be unreliable due to factual errors in their generations.
Assessing their confidence and calibrating them across different tasks can help mitigate risks and enable LLMs to produce better generations.
arXiv Detail & Related papers (2023-11-14T16:43:29Z) - Multi-Target Multiplicity: Flexibility and Fairness in Target
Specification under Resource Constraints [76.84999501420938]
We introduce a conceptual and computational framework for assessing how the choice of target affects individuals' outcomes.
We show that the level of multiplicity that stems from target variable choice can be greater than that stemming from nearly-optimal models of a single target.
arXiv Detail & Related papers (2023-06-23T18:57:14Z) - Participatory Budgeting With Multiple Degrees of Projects And Ranged
Approval Votes [0.0]
In an indivisible participatory budgeting (PB) framework, we have a limited budget that is to be distributed among a set of projects.
Each voter approves a range of costs for each project, by giving an upper and lower bound on the cost that she thinks the project deserves.
The outcome of a PB rule selects a subset of projects and also specifies their corresponding costs.
arXiv Detail & Related papers (2023-05-18T13:39:56Z) - ZigZag: Universal Sampling-free Uncertainty Estimation Through Two-Step Inference [54.17205151960878]
We introduce a sampling-free approach that is generic and easy to deploy.
We produce reliable uncertainty estimates on par with state-of-the-art methods at a significantly lower computational cost.
arXiv Detail & Related papers (2022-11-21T13:23:09Z) - Use of Bayesian Network characteristics to link project management
maturity and risk of project overcost [0.0]
This paper uses the characteristics of Bayesian networks to formalize experts' knowledge and to extract knowledge from a project overcost database.
It develops a method to estimate the impact of project management maturity on the risk of project overcost.
arXiv Detail & Related papers (2020-09-18T08:00:25Z)
This list is automatically generated from the titles and abstracts of the papers in this site.
This site does not guarantee the quality of this site (including all information) and is not responsible for any consequences.